No history of tag movement is captured. While tags can be placed moved, this is not typically done once the plan has been set. Moving a tag after the plan has been committed to, will result in an inaccurate PPC. Typically, a tag that is not completed on a given day will be left in place and statused as ‘not complete’, with a reason of variance. The card would then be copied and moved to a new date, thereby keeping a record of what actually took place and keeping the PPC accurate.
- Getting started
- Download
- Nialli Visual Planner user guide
- Using
- FAQs
- How does the system encourage engagement in pull planning sessions?
- Is the system capable of tracking a team's PPC?
- Does the system support a constraint log?
- Are chat, comment and video chat features embedded in the system?
- Is there a record of tag movement or changes for project history?
- Who can create and modify tags?
- How does the system identify the longest path?
- Is the system capable of customizing Variance reporting?
- How easy is it to add users?
- What are the steps to create a tag?
- What effort is required to maintain and update the system?
- Is system capable of import and export to and from P6?
- Is the system an enterprise or stand-alone license?
- Can comments be added to a tag?
- If a tag is moved or commitment is not met is the system capable of automatically adjusting milestone schedule?
- Inside the tag, is there a record of all changes?
- How we can retrieve or track data if some tags were accidently deleted?
- What are steps to create a new tag if you are not working on touch wall?
- What type of hardware is required and will it be supplied by Nialli as part of subscription cost?
- What is one Nialli strength as a virtual pull planning system relative to other competitors?
- What is the cost of implementation fee?
- Is a free trial available?
- What contract terms available?
- As administrators, can we pre-fill the “stickies"?
- Does the software have accessibility for mobile users?
- Can a master schedule be imported from another application?
- If there are changes on the "stickie note", can the software generate a notification to other tasks dependent upon it?
- Are interdependencies between commitments clearly visible?
- Are tags “stacked” or are concurrent tags visible?
- Who can delete a plan?
- Troubleshooting
- Release notes
- Version 1.4.29706.0
- Version 1.4.25470.0
- Version 1.4.22440.0
- Version 1.4.18190.0
- Version 1.4.16524.0
- Version 1.4.13339.0
- Version 1.4.11317.0
- Version 1.4.9996.0
- Version 1.4.8567.0
- Version 1.4.6597.0
- Version 1.4.5514.0
- Version 1.4.5247.0
- Version 1.4.5204.0
- Version 1.4.4380.0
- Version 1.4.3735.0
- Version 1.4.3731.0
- Version 1.4.3710.0
- Version 1.4.3418
- Version 1.4.3071.0
- Version 1.3.2741.0
Related Articles
How does the system encourage engagement in pull planning sessions?
One of the key design criteria for the Nialli Visual Planner application is to en...
Are chat, comment and video chat features embedded in the system?
No. However the system can work with any web conferencing application to incorpor...
Does the system support a constraint log?
Yes. Constraints can be set up and added to a tag any time during a session. They...
Is the system capable of tracking a team's PPC?
Yes. PPC is generated at any time by simply selecting the Reports function. In ad...