Add activity

Step 1

  • Right-click in the lane where you would like to add an activity
  • Click Add Activity

Step 2

  • Type in the Activity name
  • Select Trade, number of Days the activity will take, and Crew size
  • Determine if you are planning from the start date or the end date
  • The Schedule activity ID from the master scheduled may also be entered
  • Click Done
Delete

Edit activity

Step 1

  • Double-click on a card to edit the task, or right-click and select Edit tag to add any details

Step 2

  • Edit necessary fields
  • The crew size is selected in the Crew size section when creating tags
  • The actual crew size is recorded in the Actual Crew size section when updating the status of tags.
  • Add constraint to this activity to populate the constraint log (Optional)
  • Click Done
Delete